Case Study
QGP Stage 2 Expansion Project
QLD (2014) 16″ 35km, X70, Dual Layer FBE, 12 750kPa
Read moreQLD (2014) 16″ 35km, X70, Dual Layer FBE, 12 750kPa
Read moreWA (2015) 8″ 294km, X42, Dual Layer FBE, 12 750kPa The hydrotesting for this project was broken into 3 sections being 83km, 120km & 91km. The second test section required 12 temperature probes at 10km points. We believe this is the longest pipeline to be tested to AS2885.5 in Australian history.
Read morePhase 3, NSW & VIC (2016) 16″ 55km, X70, FBE, 12,750kPa & 18″ 38km, X70, FBE, 12,750kPa
Read moreEngineering support with Test Pack Preparation, various hydrostatic and pneumatic testing, flange management and pressure test reporting.
Read more